Page header
 

LOCOMOTIVE ENGINEER'S REPORTS


In April 2022 Sir Nigel Gresley returned from an overhaul which took more than six years and cost about £800,000 plus about £100,000 for the support coach. If you would like to make a donation towards the cost of this overhaul please click on the donate button.


To donate via PayPal (incl. credit or debit card):Donate

Clicking on the images will display a larger version.
Clicking again will close the window. Where an 'X' shows bottom right of the image, click on this (or use the 'f'' key) to display full size.
(You may wish to maximise your screen for this)


Jul to Dec 2022 Jan to Jun 2023 Jul to Dec 2023 Jan to Jun 2024 Jul to Dec 2024
Jan to Jun 2025 From Jul 2025
Overhaul Reports 2015-2022   Return to Home Page

From July 2025.

1 November 2025

Back at Carlisle Upperby, the left side of the tender was polished to within a foot of the top beading. The front of the loco was also polished.

Membership

A new spindle was made at Crewe for the ashpan sprinkler valve. This was waiting for us at Carlisle and was fitted.

The modified right injector overflow cap, now fitted with a threaded plug was refitted. A bush has also been made to replace the plug when the clack valve is lapped in.

The guard's door on our loaned support coach has been dragging on the floor and sticking quite badly so the door hinge was adjusted.

After a couple of days away we were back at Upperby to put in a warming fire in preparation for our forthcoming Carlisle to Edinburgh trip. The chimney cover was taken off and a fire put in. The boards to prevent water from getting in to the Cartazzi axleboxes had blown away up the yard, so were retrieved and replaced.

The next day it rained so we didn't do much prep, but the warming fire was built up and the cab cleaned. During a pause in the rain some of the bottom end was cleaned and we managed to finish the polishing to the tender sides.

The front steam heat cock had been sticking so it was stripped down. The internal telescoping valve edges where they fit inside one another were lightly chamfered which seemed to prevent the components catching so the valve was reassembled. So far it has worked satisfactorily.

The loco was greased all round and the loco put on charge.

2026 Calendar

Next day was our mainline FTR and the loco was oiled round. Although it rained we did manage to get some polishing done, but the loco was pretty clean from the work done on our visits to Carlisle over the previous weeks. At FTR the left steam sands refused to work for the examiner, though they worked earlier in the day when we tested them, but we soon got them going again.

Next day was the Carlisle to Edinburgh trip. Prep went smoothly with no problems. Servicing was later done at Joppa. On the way back there was some sustained high speed running, but we were still short of time for water in Lockerbie loop, so didn't get a full tank. This trip is a tough job for the engine and it works really hard. Back at Upperby the crew were full of praise for the loco after an exciting run.

Next day we moved from Upperby to Heaton for exhibition at their open day. The line from Carlisle to Newcastle is really nice with some great photo opportunities with old NER infrastructure, the foot bridges and gantry signal boxes. At Heaton we were turned on their turntable. I hope they keep it in use for the future. We then moved in to the shed and to our eventual exhibition location.

The next day was spent in the office, then the following day I travelled to Manchester for the Network Rail Charters conference.

The next day we were at Heaton to prepare the loco for exhibition. Due to the overhead wires we were only able to clean up to the top of the upper cods mouth door so the loco looked a little odd. The right bottom end was washed down, which the public would have access to. The left side below the handrail and the brass was polished, and the CME found the front red air cock to be loose so tightened the lock nut.

Inside the firebox was cleaned ready for relighting later for our next move to Darlington. The crown being 76C after not having a fire in for the last two days.

Mugs

The next day was the first of 2 days exhibiting the loco with footplate visits, with people waiting an hour or more for a few minutes in the cab. One of our volunteers was interviewed for TV and he did a really good job of representing us.

On the second day of exhibition the boiler water was topped up through the right injector, and a warming fire put in. We were lucky with the wind direction which took the smoke out of the shed. After filling, the right injector cap was lapped in and the valve refitted, to the interest of the general public. The TPWS temporary override was re-tagged as this is done for every mainline day of running. The coach water tank was also filled.

Next morning, still inside the shed we were FTRed. The loco brakes were adjusted in the very convenient pit/raised track in the shed. While under the loco the air pump was primed. One issue found by the examiner was that there appeared to be a leak between the trailing left cylinder release valve and cylinder casting. Not serious, or something we could do anything about at the time, so this was noted and deferred. After we had sufficient steam and air we moved the loco to the non-electrified sidings to the North West of the site.

Next day was our move from Heaton to Darlington Hopetown. To get us the right way round, chimney west at Darlington, we went round from Ferryhill to Norton then Stockton to Darlington, just days before the re-enactment of the first journey of Locomotion No1. A very special journey, including crossing the S&DR Skerne Bridge. At Hopetown we were stabled outside the A1SLT shed next to Tornado. The support coach was parked next to the 1861 shed where there is a power supply.

Next day we got on with preparing the loco for the 200th Anniversary exhibition. The firebox and smokebox were examined so that the LNWRh Duty Engineer paperwork could be completed, and with pressure on the gauge the boiler was topped up with the injector, as we planned to drop some water later to reduce the boiler water dissolved solids.

Clothing

Next day we were shunted off the pit road on to the front of Tornado by a visiting class 66. The cleaning team did a great job and by the end of the day the loco looked stunning.

With the brake blocks now getting worn they were measured and were found OK for the trip to the Mid Hants Railway. That saved us changing them at Darlington. The firebox was also cleaned and a couple of firebars replaced. The crown was at 90C and the bottom sides 65, 2 days since a fire was in.

Next day was our first with public footplate access. As usual the response was amazing with people waiting well over an hour to visit the footplate. As there was a long queue we also talked to people who were waiting. We were also visited by Prince Edward accompanied by lots of posh accents and medals, but I didn't recognise any of them. We were also visited by Peter Hendy who heads up Network rail.

Two Engineering Team volunteers, both in their 20s, showed our VIP guests the cab. Prince Edward also had a wander round the front of the loco, and he seemed to be genuinely interested. Later we were visited by the Japanese Ambassador, or so I was told, unless someone was pulling my leg. Meanwhile, I managed to drain some of the boiler and very slowly refilled from mains. A warming fire was then put in.

The next day was the 200th Anniversary of the opening of the Stockton and Darlington Railway. We were again open for footplate visits, and our Team did a great job talking to visitors all day. We were joined alongside by the replica Locomotion which later left for a trip through North Road and over the Skerne Bridge.

TOP

After closing to the public we went back on to the pit road, next to Tornado, and the opportunity was taken to shunt the P2 next to 60007, lining up 2 unique Gresley front ends. I don't think people realise that the last time an A4 and an original P2 front end could have been seen together was 1938, perhaps at Haymarket, as Cock O' The North was rebuilt that year.

Next day we again had public footplate visitors and kept a warming fire in for our FTR tomorrow. Next morning we washed out the ashpan and built up the fire for FTR. The brakes were adjusted and the loco generally cleaned, though having been cleaned for days it only took a wipe over.

With the FTR passed we filled the boiler and put a warming fire in for the night. Next morning we rebuilt the fire and put the loco on to the support coach. Beforehand we were used to shunt Tornado, which was quite a struggle as there is quite a climb from the A1 shed. At least it would have been entertaining to the onlookers in the public gallery.

We were met by the LSL footplate crew at the support coach and set off for Newark, a nice run up the ECML, taking water at York Yard North.

At Newark we were met by our Tech and Ops Manager who had earlier driven over and sorted out the Network Rail sidings for us. We ran power to the coach from a NR office and the local staff were very helpful. Meanwhile, with the loco secured, the inside axleboxes were oiled. The outside right side was oiled while I looked out, as we were near to the running lines.

Teatowel

The loco then ran up the ECML as far as Finsbury Park, taking water at Peterborough and on the other side of London, Chertsey. I wonder if we will ever run south of Peterborough again with the talk of new signalling we are not compatible with, and increasing pathing difficulties. There were plenty of spectators around to see us, in fact some footbridges and stations had as many onlookers, if not more, than when we run a normal train.

At Alton the LSL crew left us and a MHR driver took over, with one of our volunteers firing to the shed at Ropely.

Fortunately we had a day to prep before the MHR Gala. Everybody cleaned. After the last fire was disposed of a warming fire was put in. The smokebox and firebox being examined first, to complete the LNWRh Duty Engineers paperwork.

The first day of the Gala, Friday, was wet but there was a reasonable turnout. As usual at the end of the day the crew were very complimentary and reported no defects. The loco ran the next 2 days with no problems other than a couple of reports of dragging brakes. Our A4 is quite unusual in being fully vacuum braked so it's not unusual to get reports like this, also on uneven track at preserved railways the brakes can touch. However, it was noticed back on shed that the left leading vacuum cylinder wasn't fully dropped to the full brake off position.

Unrelated, at disposal the drain from the ejector was blowing more than usual due to the large ejector not fully shutting off. Again it's not unusual for the large ejector to need some TLC on preserved railways as it's the only time it gets some use. A few rapid operations of the brake handle sorted that, but it was noted to look at it further, after the Gala.

  • New spindle.
    New spindle fitted in the ashpan spray valve cap. 9 September 2025.
    Photograph © Darrin Crone.
  • Chimney cover.
    At Upperby with the chimney cover on. 9 September 2025.
    Photograph © Darrin Crone.
  • Telescoping valve.
    The front steam heat valve internal outer telescoping valve. 13 September 2025.
    Photograph © Darrin Crone.
  • Clearing steam sands.
    Steam sands being cleared after they refused to work at FTR. 14 September 2025.
    Photograph © Richard Swales.
  • Servicing at Joppa.
    During servicing at Joppa. 15 September 2025.
    Photograph © Darrin Crone.
  • Turning.
    Being turned at Heaton. 16 September 2025.
    Photograph © Darrin Crone.
  • Heaton.
    In the shed at Heaton. 21 September 2025.
    Photograph © Darrin Crone.
  • Axleboxes are oiled.
    The axleboxes are oiled. 22 Seotember 2025.
    Photograph © Darrin Crone.
  • Heaton.
    Ready for departure from Heaton. 22 September 2025.
    Photograph © Richard Swales.
  • Skerne Bridge.
    Skerne Bridge arrival. 23 September 2025.
    Photograph © Malcolm Bateman.
  • Hopetown.
    Cleaning at Hopetown. 25 September 2025.
    Photograph © Richard Swales.
  • Locomotion No1.
    Locomotion No1 arrives. 26 September 2025.
    Photograph © Darrin Crone.
  • Two Gresleys.
    Two unique Gresley profiles at Hopetown. 27 September 2025.
    Photograph © Darrin Crone.
  • Cab visits.
    The queue to visit the cab of 60007. 28 September 2025.
    Photograph © Richard Swales.
  • Taking water.
    York Yard North. On the way to Newark we take water at York. 30 September 2025.
    Photograph © Scott Middlemiss.
  • Newark.
    Next to the main line at Newark. 30 September 2025.
    Photograph © Scott Middlemiss.
  • At Alresford.
    At Alresford waiting to take the first train of the Gala. 3 October 2025.
    Photograph © Darrin Crone.
  • Tender brakes.
    Adjusting the tender brakes. 5 October 2025.
    Photograph © Darrin Crone.
  • Departing Ropley.
    Departing Ropley for Alton. 5 October 2025.
    Photograph © Scott Middlemiss.

18 September 2025.

In hot sunshine we cleaned the loco with a full support crew in attendance. By the end of the day it looked superb. Some prep was also done with checking sands and examining the axleboxes.

With the same crew in attendance, the next day was our FTR. At the FTR a couple of tender spring end screws were found loose so were tightened. The left gravity sands would not flow, due to damp sand, as we had a lot of rain during the night. The sand pipe was removed and the sand valve unclogged.

Next day we worked a Carlisle to Edinburgh trip. It was a very hot day and was tough work for the fireman. In addition the trip is tightly timed and the loco works really hard. We serviced at Joppa carrying out our usual exam, oiling and cleaning the fire.

One advantage of this job is that we get back on to shed in the early evening which gives us the chance to dispose of the loco in time to be able to travel home.

Back in the office the trip documentation was completed. I also got a printed copy of the modified brake schematic for checking, and collected the plates ordered to make a jig to hold the safety valves during their annual exam. I also collected a profiled drawbar spanner from the profilers.

The following Monday we were back at Upperby to clean the firebox and do some other jobs. The firebox was cleaned and some of the firebars condemned. The whole grate is getting a bit tired now, good job we have plenty of spares, though unlike last year the coal isn't burning firebars every trip.

The smokebox was cleaned out. The ash round the left steam pipe showed that there was no air being drawn in after the seal was repaired back at Crewe. With the firebox and smokebox cleaned and examined the final parts of the LNWRh paperwork for the last job was completed. Pre-emptively the tender spring end screws were nipped up, a couple having loosened off.

We have a datasheet listing the spanner sizes for those parts we normally work on. This helps us plan jobs when away from the loco and saves time in getting the right spanner. It hasn't been reviewed for a while so the opportunity was taken to do a review and add some omissions.

To protect the tender tank from corrosion we always like to leave it full, so it was filled and treatment added. We then went on to fill the coach water tank.

At disposal after the last trip, water was seen on the left clack cap. It had been OK all day but when the loco was cooling a bead of water was seen, so it was decided to take the cap off and examine the joint. The cap and clackbox joint was cleaned and lightly lapped in. The clack valve was taken out and cleaned, and this also lapped in. It was surprising how much deposit there was on the valve and the pitting on the surface, seeing that it was only refurbished in April this year. With everything cleaned up the clackbox was reassembled.

As were weren't due to run for a few weeks the chimney cover was put on.

As noted earlier I wasn't happy with the sound of the right clack in operation, and on the last trip the fireman reported that the right injector needed occasional trimming, so it was decided to examine the clackbox. On the last trip I had also seen an occasional wisp of steam from the overflow indicating the steam valve needs attention. This clackbox hasn't been looked at since March 2024, and this side gets most use. The clack cap was removed and the cap and clackbox cleaned up and lapped. As we don't have access to a lathe at Upperby the clack would have to be skimmed and brought back later. The steam valve couldn't be removed as the LNWRh support coach didn't have a suitable spanner.

Also on the last trip it was seen that the ashpan sprinkler valve had been passing as water was seen running out of the ashpan. The cap of the valve was removed, to find that the valve spindle was cracked. The spindle was taken so that it could be used as a pattern for a new one. The valve is not an authentic LNER valve so isn't as robust as Doncaster would have made it. I think we will have to modify its design to make it more reliable in future.

It was seen previously that the small ejector, when starting from cold, fizzes where it seals on to the ejector body. It's done this before. The valve was removed and the faces cleaned and lapped in. The valve was then lapped to the small ejector cone. By the look of the lap mark it looks like the valve and cone are not perfectly aligned, though it looked like a continuous seal is made.

To ensure the gravity sands lever locates in the catch and avoid it coming out, the catch plate was re-shaped to take out wear.

The fit of the profiled spanner designed to fit the main intermediate drawbar nut was tried and the fit of the jaws is good, so now we'll make it into a usable spanner. The space is very confined where the nut is, so it is planned to make a special spanner to fit we can drive with a socket on a long bar, similar to the spanners we made for the injector pipe unions under the cab.

Back in the workshop the right clack valve was skimmed to clean the sealing face, and the aluminium packer for the right cab injector pipework was drilled and tapped with the aim of securing it to the pipe strap as it has a habit of working out.

After the weekend I went to Crewe to collect some tools we were short of in our loaned support coach, including our valve lapping jigs. While at Crewe some of the defect paperwork in the engineering office was filled in for the work we did at Upperby. After loading the van with tools and firebars at Crewe, and calling in our store, I travelled to Upperby.

Next day at Upperby the lubricator sieves were cleaned.

The air pump exhaust U bolt just above the trailing coupled axle was fitted with new locknuts, as at a recent FTR the U bolt notes were noted loose, so they were tightened and locking nuts added. Unfortunately we didn't have any thinner (lock) nuts so we fitted standard nuts. They were OK but were on the end of the threads, so proper locknuts were obtained and fitted.

With the ashpan spray valve spindle still out for copying, the valve was lapped in ready for refitting.

In the firebox some more cleaning under the outer fire bars was done before fitting the spares brought from our stock at Crewe. The 3 bolts holding the firehole protector plate were found loose so were tightened. Due to the heat, no doubt, they do loosen off, sometimes loosing a nut.

The right cab injector pipework strap was drilled for a screw for the packer. The assembly was then refitted.

Periodically we improve the ash sealing at the front of the loco. We've fitted lap plates and angles to the footplate in front of the smokebox door to ensure ash doesn't find it's way between the frames. We also fitted some plates over the frame lifting holes and now we are going to fit a plate over a hole in the bulkhead plate over the front buffer beam. At sometime in history a hole was cut in the plate, and another in-line in the front casing, though this was welded up. The hole was measured up for a blacking plate to be made.

The right clackbox steam valve was removed, now we had our spanner form Crewe. The valve and clackbox face were cleaned. Outside steady progress was made on washing the bottom end of the loco.

Back in the workshop the right clackbox steam valve was on the bench and being examined. This valve has never opened as far as the left, though it complies with the BR(E) standing order for minimum travel. The steam valve is a refurbished item at the last overhaul, fitted in to a new clackbox. At overhaul the spindle was modified as it was over-long. This increased it's travel. With the agreement of the CME it was decided to modify the nose of the valve to reduce the restriction to the flow of steam when opened. The valve was skimmed to provide a new sealing face and the nose reduced in diameter. The threaded section of the steam valve was found to be longer than drawing. It matches the valve, but to prevent the thread from running out in the body of the valve it was modified to drawing.

The ashpan spray valve was also modified to allow the wall thickness of the spindle to be increased, reducing the chance of it cracking in future. A drawing was produced of the spindle and the modifications to increase it's strength. The drawing, old spindle and valve cap were sent to Crewe for a new spindle to be machined.

Our summer break at Upperby soon continued with the fitting a new compression cap to the disused air release pipe between the frames.

The main reason we were at Upperby this week was to do a boiler water change. We drained the boiler while connecting the right injector overflow to the mains so as to flush through as much as we could. This required the removal of the injector overflow clack. With the boiler stood for a while hopefully most of the contamination was in the foundation ring anyway. We had planned to refill from the tender using a petrol powered pump, however we found that the fitting we needed wasn't the correct thread to fit the pump, so, we filled from the shed tank. Fortunately the tank, known for refilling really slowly was full enough next day to water 70000 and its train.

With the skimmed right clackbox steam valve returned, the valve seat in the clack box was lapped then the valve lightly lapped. The valve assembly was then reassembled in to the clackbox body.

The brass 25% cut off pointer plate next to the cut off indicator was fastened with steel screws. These have now been replaced with brass semi raised screws, and it looks a lot better. It was found that the screws go into rivet nuts and the right one was loose, so this was pulled up as tight as possible, but the nuts are a little short for the thickness of the backhead cladding.

With the right clackbox reassembled the cab was clear to remove the M8 valve cover to remove the aluminium pop rivets used for securing the brass position plate for replacement with more authentic looking brass screws that we bought for the 25% cut off plate. The pop rivets were drilled out and the holes in the cover tapped for the screws. The brass plate was countersunk for the new screws. Additionally lock nuts were put on the back of the screws, then the cover was refitted and very smart it looks.

A plate was made to fit over a hole in the vertical bulkhead plate above the front loco bufferbeam. The plate and bulkhead were drilled through for bolts and the plate painted to primer. It was then fitted. This will improve the ash sealing to the inside of the frames.

The gravity sands catch recently reshaped, was painted. Meanwhile outside the bottom right side of the loco was washed down. While the paint was out, the chains on the oil and lamp cupboards were painted.

Next day, due to heavy rain, we sheltered in the LSL support coach and fitted a new light in the workshop as the old one had stopped working some time ago.

A mounting board for the oil cupboard has been made and fitted. This means that the grease gun and siphons can be clipped to the back of the cupboard rather than everything sitting on the bottom.

Also woodworking, the spare gauge glass box was drilled out to better fit the longer glasses we've been using for some time now.

In the drier weather the lower half of the right side of the tender was polished. Later coal was moved forward ready for lighting up for our next Edinburgh trip.

The right injector overflow clack was lapped in, and the cap taken to modify it to allow it to be used as a lapping guide.

  • Boiler top.
    .Before and after cleaning the top of the boiler after one trip. 11 August 2025.
    Photograph © Darrin Crone.
  • Sprinkler valve.
    The ashpan sprinkler valve allowing water to pass and wetting the sleepers. 13 August 2025.
    Photograph © Darrin Crone.
  • A Joppa.
    A Joppa during our serving stop, the fire is cleaned. 13 August 2025.
    Photograph © Cameron Calvert.
  • Sprinkler spindle.
    The ashpan sprinkler valve spindle found cracked. 19 August 2025.
    Photograph © Darrin Crone.
  • Small ejector body.
    The small ejector body removed for lapping showing original manufacturers part number. 19 August 2025.
    Photograph © Darrin Crone.
  • Clackbox steam valve.
    The right clackbox steam valve after having thread shortened and valve shape modified. 31 August 2025.
    Photograph © Darrin Crone.
  • Water changing.
    Water changing at Upperby. 2 September 2025.
    Photograph © Richard Swales.
  • New plate.
    A new plate covering a hole in the front of the loco preventing smokebox ash ingress. 3 September 2025.
    Photograph © Darrin Crone.
  • New brass screws.
    New brass screws fitted to the 25% cut off plate. 3 September 2025.
    Photograph © Darrin Crone.
  • New brass screws.
    New brass screws in the air brake position plate. 4 September 2025.
    Photograph © Richard Swales.
  • Storage box.
    The spare gauge glass storage box modified to accommodate the longer glasses. 4 September 2025.
    Photograph © Darrin Crone.

22 August 2025.

The first day of this report we were on prep. day for a move from Crewe to Upperby, Carlisle for the following day's trip to Edinburgh. We did the usual prep of oiling and cleaning.

Quite a few "loose" nuts were found during the FTR. Some needing a flogger to get them to move, so not that loose after all.

The major issue at FTR was the injectors. Both were wasting, which is a big change from the last time the loco was steamed when they were both dry and reliable. It was a hot day and the tender had been outside for some days so it was thought that the water in the tank might be warm and affecting the injector efficiency, so we put a few hundred gallons of mains in, but there was no change. To me the clackboxes sounded woolly. Something was obviously not right. The injectors did waste but they certainly put water in the boiler so examiner decided to pass it for the following days trip. As a quick check the combining and delivery cones were taken out of the right injector. They looked OK and so did the inside of the injector body, as far as was visible.

Another complication on prep day was accessing the support coach. It had been parked in an inaccessible location and was only shunted to us later, so we had to move our equipment and personal gear when we could.

Early next morning, as advised by the CME the right injector which has a hose connection on the overflow, was flushed through in to the tender, in an attempt to clean the flow path from the tender if it was obstructed. To do this the injector overflow clack was removed. After back flushing the performance of both injectors was improved. This indicated we had a problem on the water delivery side that we would have to investigate further later. The injectors ran well on the road, not as good as they used to, but at the Preston water stop it was noticed that the right injector cap was leaking.

we had to prep for the next days trip to Edinburgh. We had serviced before but hadn't stayed there so there was some setting up to do but we soon had the coach on mains power and the loco charging. We were on a pit so we oiled the inside axleboxes cleaned the fire. Outside, the loco a had a wash.

Next morning the loco prep was completed. We had a good run to and back from Edinburgh with some hard work from the loco.

At Edinburgh we went to Joppa for servicing. The fire was cleaned, and some clinker was paddled out. Otherwise it was our standard service with big and little ends oiled and the big brass siphon boxes refilled. The mechanical lubricators were examined but didn't need a top up.

Back on Upperby temperatures and oil levels were recorded. The fire was levelled and the boiler filled. While waiting for the boiler to fill the loco and tender brakes were adjusted ready for our move back to Crewe the next day.

Next morning the loco ashpan was washed out and the loco prepared for its trip back to Crewe. On the way back it was reported that again there was an improvement in the operation of the injectors.

At Crewe the loco boiler was filled, loco examined and we were finished early enough to travel home, which was a nice change.

Back in the office the records of our recent runs was compiled and the LNWRh paperwork completed.

In the home workshop an aluminium packing piece for the right injector pipework was made to replace the wooden one that had split.

After the weekend, back at Crewe we were scheduled a washout. We had planned to fit the blowdown at this washout to take advantage of the drained boiler and the steam test. However, eventually we didn't have the time to fit it, even with the steam test delayed to the day before the next Fitness to Run exam for our next mainline trip. With the time available we set about other jobs.

One of the jobs to do was to examine the inside of the tender and in particular the sieves through which the injectors draw water. So, the tender was drained. The tender can be drained through the injector overflows or by removing the drain caps under the tender. Removing a cap always results in getting wet and/or loosing the seal, so we drained through the overflows, but this is a long job.

While the tender was draining the firebox and ashpan were cleaned. As the washout requires the removal of the smokebox plugs the primary spark arrestor screens need to be removed and the smokebox thoroughly cleaned of ashes.

The left steam pipe looked to be drawing air where it goes through the smokebox side. This had been noted previously by our CME. It was also noted that there was a lot of steam oil about the left piston rod and union link so it was planned to check the atomisers.

The boiler was drained and the boiler blisters were removed while the LNWRh boilershop removed the boiler doors and plugs. The boiler was still quite warm and steamed from the opened doors so was left the rest of the day to cool a bit more before washing out with cold water.

The tender was now empty so the inside of the tank was examined and the bottom and the sieves were found to be covered in a thin fine deposit. It didn't readily wash off but was easily dislodged with a brush. The sieve box was removed and cleaned and the sump and other surfaces brushed and washed out. The pipes and hoses from the tender were also hosed through and they seemed to be clear. The sieve box was then refitted and the hoses reconnected between the loco and tender.

With the tender empty and the trailing sump plug off we tried the new drain valve on, however the thread on the tender is not a standard BSP thread. The thread was measured accurately and the dimensions with the valve given to LNWRh to make an adaptor. This new valve means when we want to drain the tender in future it should be much quicker and we can connect a hose, meaning the tender tank can be used as a water supply, or it can be drained away from the loco.

As mentioned earlier it was noticed that the left steam pipe was drawing air in to the smokebox. To remake the seal the sealing plates need to be removed and this was done. The nuts had to be burnt off then the plates were removed and cleaned, along with the sealing areas on smokebox plate and steam pipe.

The right injector cap seen leaking was taken off and the overflow clack taken out to have its face skimmed. The clack was given to LNWRh to quickly skim up. The injector cap was cleaned up and lapped back in and hasn't given any trouble since.

In discussion with Boilershop it was decided that we didn't have time this washout to fit the blowdown, and with the cancellation of the Scottish jobs we should have time to do sufficient water changes before we are due to return to Crewe in October.

Before we can commission the blowdown, the blowdown valve needs overhaul as it hasn't been used since fitting. In the meantime it was decided to fit the old blanking plate fitted before the last overhaul and retrieved it from our store. So, the valve was taken off and we modified the old blanking plate to the same footprint of the valve so we knew it would fit in the current space. We also cut a new gasket for under the plate. The plate was then fitted as part of the job to refit the boiler doors and plugs after washing out. With all the plugs, doors and blanking plate fitted, we refilled the boiler for lighting up.

The blowdown valve was cleaned down and left with Boilershop for overhaul. It is also planned to make an inlet filter to prevent any foreign objects jamming the valve open.

The new aluminium packer for the right cab injector pipework was fitted to replace the split wooden one. While there the steam heat gauge pipe that runs over the injector pipework was annealed and bent away from the pipes as it looks like it had rubbed at times.

A new sealing rope was fitted around the left steam pipe in the smokebox. The rope was then covered in fire cement and the sealing plates refitted. This time extra washers were put on the bolts which will make the nuts easier to burn off next time.

The cab seat cushions have worn through and split. Their biggest enemy being hot fire irons and other tools. We had spares but I've held on to them until we were due to go to Derby. It wasn't that straight forward, as the fireman's seat base had to be bent to make it level for the cushion, and some old bolting on both seats had to be cut off and drilled out due to being stripped or having corroded threads.

It was mentioned earlier that the left piston rod and union link seemed very oily so it was decided to examine the atomisers. The outlet pipes were taken off and the lubricator pumped. The right all fed well and the baffles were clean and clear. A small wire was used to feel the steam side balls and they seemed OK. The left when pumped didn't all feed the same, it appeared, and I couldn't feel the balls. The baffles were clean and clear though. So, it was decided to take the left atomisers out and examine them. Opening the atomisers up all appeared well, in fact they seemed to be cleaner than I remember them. All the balls were clear and there was no contamination anywhere. So they were refitted.

The tender drain valve adaptor was now available so was fitted to the tender. The tender was then filled with water and the drain valve assembly examined for leaks. It was tight. For safety the valve handle was removed to ensure it doesn't get caught on the road and empty the tender. The handle is currently in the cab toolbox for when we need it.

After the weekend we were straight in to steam test, the loco being lit the day before by Boilershop. Both injectors worked cleanly though the drivers side needed setting of the steam valve. That's new. The fireman's side was back to normal.

As the steam test progressed the mechanical 28 day exam was carried out and we attended to some repairs. The left tender brake piston rod gaiter was changed.

The lock nut on the loco front yellow air valve was found loose so this was tightened up, but more significantly a crack was found in a frame stretcher that supports the upper loco brake pull swing links. The crack was found near an historical weld. The stretcher seems to have been modified at some time with a new section welded in. Looking at the arrangement, to fully access and repair would mean considerable work in removing the stretcher, probably why a section had previously been let in. So, it was decided to weld on a new patch plate and monitor its performance. When the opposite end of the stretcher was examined this too was found to be cracked so patch plates were welded on both ends. Before welding the loco electronics had to be disconnected.

With the steam test complete the spark arrestor primary screens could be refitted. This was left until the next morning so that the smokebox could cool down a bit, but with the FTR to complete that day we had to leave a warming fire in, so it didn't cool down that much. So in a very hot smokebox the screens were refitted. Not something I want to do again, ever.

The weather was damp so it was a good job we'd done a fair amount of cleaning the day before. Today the loco was just washed with the bottom end received more cleaning. Also today the drivers side injector worked fine with the steam valve wide open, so pretty much back to normal.

The final prep was done with oiling round and greasing. As the weather cleared most had a go at polishing the brightwork.

Next day we moved to Derby. At prep the ashpan was washed out and the fire made up.

We arrived at Derby at about 0915 and waited for a shunt in to position, which was achieved by 2030. Upon arrival at Derby it was noticed that there was a lot of steam oil on the coupling rod beneath the mechanical lubricator. We tracked this down to a mechanical lubricator oil pipe where it passes through a hole in the footplating. While parked we put up a stop board and took out the pipe to find it had been chafing and had worn a hole. The one next to it was also removed as running a finger along it a depression could be felt. This too was a chafe mark but it had not worn through. The pipes were labelled up and sent back to Crewe for repair.

On our lubrication drawing it showed the holed pipe ran to the inboard left atomiser which feeds the left cylinder. Strange that earlier it was noted that there was more oil at the left piston rod.

The next day was spent cleaning the loco, which on top of the previous clean and relatively low mileage to Derby made the loco gleam. The cab was cleaned by our expert cab cleaner. We still waited to be shunted for the east coast line up, but that never came, though we did eventually find a shunter to pull the A2 off the front of us.

Next day the Greatest Gathering was opened to the public. We were very popular but we waited for steps to be put up so people could visit the cab. We did mange to get some members in the cab but couldn't let general public climb in to the cab. Next day the steps were provided and we did good business with the team proud to show their engine off.

For a spell a genuine Yorkshire Pullman headboard was put on, which was a nice touch.

We had a very successful visit but it was soon Monday and we had to light the loco for FTR on Tuesday.

The repaired oil pipes were brought from Crewe. They were fitted and where they pass through the footplating they were wrapped in rubber. The mechanical lubricator was then pumped until oil was seen at the oil bleeds at the atomiser.

Next day was our FTR. The loco was driven on to our coach which was in the shed and coupled up. We watered while in there, and the staff were surprised that we filled their unventilated shed with smoke.

Next day, in steam, we were assembled with a couple of diesels and 60532 for the trip back to Crewe. On the way, of all things, the AWS acknowledgement handle failed. Back at Crewe we had the afternoon to sort it as we were to move to Carlisle next day. No pressure there then.

While we set about taking the sunflower box apart to access the handle mechanism I managed to find 60019's which is a similar unit. We and LNWRh came up with a solution involving a securing bracket to hold the internal rubber torsion spring. The bracket was made and fitted then tested and approved by LNWRh. It feels stiffer and much more positive than I remember so I suppose it was on its way to failing for sometime.

As we had time next morning we left the oiling to be done until before departure. At Carlisle the loco was made safe and the boiler filled. We then made our way back to Crewe then home.

After a couple of days away, including an office day, we were back at Carlisle to prep for a trip to Edinburgh. Pit boards have now been provided so these were set up either end of the loco and support coach. Then the firebox was cleaned, and with enough water in the boiler a small warming fire was put in. .

  • At Upperby.
    At Upperby after an Edinburgh trip being prepped for return to Crewe. 16 July 2025.
    Photograph © Richard Swales.
  • Uperby.
    Upperby sunrise. 16 July 2025.
    Photograph © Darrin Crone.
  • Carlisle.
    Awaiting the signal to Edinburgh at Carlisle. 16 July 2025.
    Photograph © Darrin Crone.
  • Joppa.
    Servicing at Joppa. 16 July 2025.
    Photograph © Darrin Crone.
  • Joppa.
    Servicing at Joppa. 16 July 2025.
    Photograph © Darrin Crone.
  • Crewe.
    Washout at Crewe. 23 July 2025.
    Photograph © Darrin Crone.
  • Drivers' seat.
    Drivers seat'. 23 July 2025.
    Photograph © Darrin Crone.
  • New seat.
    New driver's seat cushion. 24 July 2025.
    Photograph © Darrin Crone.
  • Drain valve.
    The new tender drain valve. 24 July 2025.
    Photograph © Darrin Crone.
  • Cab.
    The cab cleaned for showing to the public at the Greatest Gathering. 31 July 2025.
    Photograph © Darrin Crone.
  • Headboard.
    With a real Yorkshire Pullman headboard. 2 August 2025.
    Photograph © Frankie Hutchings.
  • Derby.
    In the shed at Derby with 60532. 5 August 2025.
    Photograph © Richard Swales.

26 July 2025.

Back at Crewe the oil in the outside little ends was examined. Both had now settled down to a normal colour without the froth. Meanwhile our gear was moved from the support coach used on the last trip, back in to our own coach for safe keeping.

The design change paperwork covering the modification to the outside little end covers to allow oil level dipping was sent to LNWRh.

While discussing the OTMR system with LNWRh, with a view to adding additional sensors, it was noticed that the covering to the flexi conduit to the AWS sunflower box was damaged and the conduit needed recovering. This was noted and dealt with later.

Examining the loco it was noticed that the right gravity sands lever on the top of the sandbox was contacting a bank of lubrication pipes. Again this was dealt with later as the job in hand was to clean the firebox from the last trip, before the loco was shunted in to the shed. After the loco ashpan was cleaned out the loco was shunted inside and we emptied the pit.

In the shed the loco brake blocks were changed.

The crank axle was measured using our routine monitoring procedure.

At new clackbox clack lapping jig has been made by our CME and it is now in our toolbox with our other special tools.

Outside the loco, the rods were cleaned while the drivers cab floor was taken up, as one of the screws holding the floor down was loose and won't tighten. With the floor up the batten the screw went in to had a number of old holes in, so it was decided to fit a new batten. The new batten was drilled through and fastened to the cab floor structure. A new screw was then used to fasten the cab floor down. While working on this section of floor, a screw was put through the TPWS front conduit protection box as it tends to get knocked and displaced by drivers feet.

On the last trip it was noticed that now and again the air pump lubricator missed a stroke, so the outside roller clutch was examined. The return spring was also examined as it has been known to break. The spring was fine and the roller clutch was cleaned out and operated satisfactorily when reassembled. It has worked fine since so it might have been some contamination. Anyway, the rollers look to have seen some water at some time by their surface marking so we plan to fit new rollers.

A reported defect was an oil leak to the left side of the bogie stretcher, so this was investigated. The cover was removed and the void inside cleaned out of oil. There was no signs of an oil leak and it is thought that the oil is from the middle valve guides which drip on to the bogie stretcher. We will have to periodically clean this out to stop alarming FTR examiners.

The new intermediate air hoses were fitted with date tags as the Crewe system requires. We couldn't do this when the hoses were fitted as there were no tags available.

The blowdown exhaust pipe and silencer were trial fitted after new pipes were made. The silencer is secured on an air pump stud, which will have to be made longer to allow a full nut to engage.

After a spell in the office on our engineering procedure paperwork we returned to Crewe. While the left side of the loco was polished, we checked the latest version of our brake schematic. The latest version had been produced by the CME's office, and a hard copy printed off the week before. A number of comments were added to the drawing and the drawing was sent back to the CME.

In the coach's guards compartment some touching up of the paintwork has been done, and the lagged steam heat pipe painted. It was previously unpainted.

The brake system schematic check required the cab floor to be lifted. With this now complete the floor was put back down and the toolbox put back under the firehole door. It was discovered that the toolbox bottom is worn very thin and holed in places.

The flexi conduit to the AWS sunflower box was re-wrapped.

Our new "Emergency Equipment" labelling was put on the lamp cupboard replacing the temporary labelling, and the new labelling by Richard Green looks great.

Our new firehole blanking plate seems to have worked very well keeping smoke out of the cab, so it was fitted with a couple of steel strip loops to act as springs to keep it tightly in place behind the firehole door.

A new chain and hook were fitted to the oil cupboard to replace the old rather light chain and lynch pin which was troublesome to use when having an oil can in your hand. The new hook should be easier to use and looks more in keeping with the loco.

The oil hole to the handbrake handle socket was cleaned out. There was a fair bit of coal in there, slowly grinding away. So cleaned out, the handbrake was oiled and a cork fitted in the hole to keep it clean. Hopefully this will solve the stiff handbrake.

The coach wheelset bearings were removed when the wheels were re-tyred. They have been examined and a number have been rejected for further use. In balance it was decided to renew all the coach bearings. This is a significant cost, about 60% of the cost of new tyres. After some thought and consulting experts, we bit-the-bullet and placed the order. They are also on a long lead-time which means we won't have our support coach for the rest of 2025, so more moving our gear from coach to coach. Work we could do without.

Back at Crewe with a few hours to spare we went to our container to do a bit of sorting out and stock taking. A very productive visit and we will have to do more.

Back in the shed the gravity sands operating gear was adjusted and we could not reproduce the position of the right lever anywhere near the lubricating pipes. The operation of the gear was tested, making sure the sand is shut off but the travel is limited to avoid contact with the pipes.

It was noticed that one of the coupled axlebox top cover screws looked high as if it had unscrewed. This is not unusual and has been seen before. It could not be accessed with a screwdriver so it was knocked round with a long chisel. The other screws where examined and they were all tight.

The air pump exhaust pipe drips water where it goes in to the middle cylinder block on it's way to the chimney. This drips on to the leading brake stretcher, pools and runs off, normally on to whoever goes to examine the middle engine during servicing. So the leaking joint was wrapped with a tape.

A long stud was fitted to the air pump to allow the blowdown silencer to be secured, meanwhile outside the bottom end of the loco was cleaned all along the right side. The ongoing cleaning of the loco is very important as it releases support crew from cleaning to get involved with the loco preparation and dealing with FTR issues.

We have empty holes on the loco bottom cab footsteps. They were used for brackets that supported the injector overflows. The right previously being an exhaust steam injector. The holes have now been filled with large countersunk slot screws of the type used for the brackets.

During disposal the ashpan screen is held open on the damper with a U clip on a chain. A hook has now been added to the clip so it can be hooked up on it's chain and prevent it from swinging against the loco when running.

The pipes that run to the air brake duplex gauge in front of the driver, are otherwise unsecured between the gauge and the cab floor. They are very near a washout plug and a cladding bolt head and are in danger of damage so a clip was made and they are now secured.

Our steam oil bottle has a leak and overtime oil runs from the bottom of our cab oil cupboard. Some time ago Crewe gave us a new oil bottle. Well not so new, with a few dents but assured it did not leak from it's base. The bottle was cleaned down and repainted by us. The bottle also didn't have a stopper so we made one.

In the cab, occasionally when running, the injector pipework vibrates. To prevent this the pipes were wrapped together with copper straps, with wooden packing pieces between the pipes as they are separate. The packers were made by the joiner in the LNWRh joiners shop. While fitting the strap to the left pipes it was found that the steam chest pressure gauge pipe was contacting the outboard injector pipe, so it's clip was modified. Now the steam chest pipe runs between the injector pipes.

While the new air duplex pipe clip was being painted the M8 stand was also touched up.

After a couple of days at home we were back at Crewe to carry out a boiler water change and put in a warming fire for our next trip. As the fire was catching and the loco warming, a chain was put on the stopper of the new oil bottle.

  • Bogie stretcher top.
    The bogie stretcher top with cover off and cleaned out. 18 June 2025.
    Photograph © Richard Swales.
  • Blowdown silencer box.
    The blowdown silencer box trial fitted. 18 June 2025.
    Photograph © Darrin Crone.
  • New batten.
    Under the driver's floor a new batten to fasten the floor. 18 June 2025.
    Photograph © Darrin Crone.
  • Flexi conduit.
    The flexi conduit re-wrapped. 2 July 2025.
    Photograph © Darrin Crone.
  • Lamp cupboard.
    New labelling on the lamp cupboard door. 2 July 2025.
    Photograph © Darrin Crone.
  • New chain and hook.
    New chain and hook on the oil cupboard door. 3 Juy 2025.
    Photograph © Darrin Crone.
  • Air pump exhaust pipe.
    Wrap to the air pump exhaust pipe . 8 July 2025.
    Photograph © Darrin Crone.
  • Injector screws.
    Screws for the injector overflow brackets. 8 July 2025.
    Photograph © Darrin Crone.
  • Guard's compartment.
    The guard's compartment paintwork. 8 July 2025.
    Photograph © Darrin Crone.
  • Draining the boiler.
    Water change draining the boiler. 13 July 2025.
    Photograph © Darrin Crone.
  • ir duplex gauge pipes.
    New clip on the air duplex gauge pipes. 13 July 2025.
    Photograph © Darrin Crone.
Jul to Dec 2022 Jan to Jun 2023 Jul to Dec 2023 Jan to Jun 2024 Jul to Dec 2024
Jan to Jun 2025 From Jul 2025
Overhaul Reports 2015-2022   Return to Home Page

Return to top

Copyright © The Sir Nigel Gresley Locomotive Trust Ltd